By its decision of 4 November 2022, the Vaasa Administrative Court upheld the environmental permit package granted to Metsä Group’s Kemi bioproduct mill. On 18 December 2020, the Regional State Administrative Agency for Northern Finland granted environmental and water supply permits for the Kemi bioproduct mill.
Three appeals were filed against the permit during the period of the permit’s availability, to which Metsä Fibre submitted a response to the Vaasa Administrative Court on 2 September 2021.